- execution of fine plasters and mortars in the interiors
- painting of external plasters
- painting part of the interiors, cellars, painting of arcade corridors
- restoration of wooden façade windows
- restoration of door frames and door leaves - workshop work
- restoration of façade window sashes - workshop work
- masonry work
- execution of plasterboard partitions
- construction of air conditioning pipes
- construction of pipe insulation
- installation of heating elements in the section
- assembly of wooden door frames of arcade corridors
- laying of a new ceramic floor of the arcade corridor
- restoration of the original floor in the arcade corridor
- installation of ventilation systems for social facilities on the ground floor
- execution of stone facings of external stairs
- electrical installation work
- heating works, heating tests, heating launch
- laying of ceramic floors in the technical rooms
- 11th inspection day
|